Swapan Dasgupta said the government wants to hold a special session of the Assembly in the future to discuss the CAG reports
โ62,632 outstanding UCs of โน 92,132.75 crore were yet to be received by the Principal Accountant General (Accounts & Entitlements), Bihar as on March 31, 2025โ, said the CAG report under the title of โFinancial Reporting Practicesโ, which was laid on the floor of the state assembly on July 23
Congress cites the CAG report, alleging the scheme was rolled out despite warnings from the State finance department about its sustainability
CAG reports finds that out of the Corporationโs 143 vehicles, 72 had to be auctioned off as unserviceable, while another 34 were off the roads for want of fitness or maintenance
Project cost rose from โน18.83 crore to around โน61 crore; audit also found unresolved basement waterlogging and pending works